UNISEL SDN BHD (Dahulunya dikenali sebagai PENDIDIKAN INDUSTRI YS SDN BHD) v SUDITASIA SDN BHD

ba-22ncvc-80-02-2023 High Court (Mahkamah Tinggi) 4 May 2026 • BA-22NCvC-80-02/2023 • 25 min read
26 cases cited (0 SG, 26 foreign)

Catchwords

Contract — Development agreement — Landowner and developer — Development of 50 acres of land — Defendant appointed as developer — Failure to complete development — Only part of project completed — Substantial portions remained unbuilt — Whether developer breached development agreement — Whether completion of “Phase 1” amounted to substantial compliance — Held: Defendant breached the Development Agreement. Contract — Construction and development project — Approved plans — Developer’s discretion — Whether developer had absolute discretion as to number and type of units — Clause requiring development to be carried out in accordance with approved plans and authority requirements — Held: Defendant’s discretion was not absolute. Contract — Time for completion — 48-month completion period — Whether time was of the essence — Subsequent dealings between parties after expiry of completion period — Whether time became at large — Commercial parties attempting to preserve contractual relationship — Held: Defendant still obliged to complete within contractual period or, alternatively, within reasonable time. Contract — Frustration / impossibility — Section 57 Contracts Act 1950 — Gravesite issue — Subdivision and pre-computation plans — Regulatory and administrative difficulties — Whether performance rendered impossible — Held: Practical difficulty not equivalent to legal impossibility. Contract — Prevention principle — Duty of cooperation — Alleged refusal by landowner to execute revised documents — Landowner’s right to protect proprietary interest — Whether Plaintiff prevented Defendant from performing — Held: No sufficient act of prevention established. Contract — Default and takeover clause — Clause 17 Development Agreement — Notices of default — Whether notices sufficiently identified default — Whether Plaintiff validly invoked contractual right to take over project — Commercial notices not to be construed with undue technicality — Held: Clause 17 validly invoked. Limitation — Contractual claim — Whether claim time-barred — Plaintiff’s claim arising from Defendant’s failure to comply with Clause 17 notices and refusal to give effect to takeover — Not merely claim for damages for non-completion in 2011 — Held: limitation defence not established. Equity — Waiver, estoppel and laches — Continued cooperation after expiry of completion period — Non-waiver clause — Whether Plaintiff abandoned contractual rights — Held: no waiver, estoppel or laches established. Equitable remedies — Mandatory injunction — Specific performance — Development agreement involving continuing obligations and supervision — Defendant itself in breach — Whether Court should compel continuation of commercial relationship — Held: mandatory injunction and specific performance refused. Damages — Counterclaim — Loss of profits and development expenditure — Requirement of proof — Speculative figures — Double recovery — Section 74 Contracts Act 1950 — Hadley v Baxendale — Held: Defendant failed to prove damages and counterclaim dismissed. Result — Plaintiff’s claim allowed — Defendant declared in breach of Development Agreement — Plaintiff validly invoked Clause 17 — Defendant ordered to return title and project documents — Defendant’s counterclaim dismissed — Costs awarded to Plaintiff.

Practice Areas

Judges (1)

Counsel (7)

Parties (2)

Statutes Cited

Cases Cited (26)

UK (2)
[1904] 2 KB 264 [1941] AC 108
MY (24)
[1971] 1 MLJ 32 [1973] 2 MLJ 1 [1984] 1 MLJ 186 [1987] 1 MLJ 171 [1987] 1 MLJ 302 [1990] 1 MLJ 374 [1993] 1 MLJ 113 [1995] 2 MLJ 317 [1996] 1 MLJ 655 [1998] 2 MLJ 120 [1998] 6 MLJ 65 [1999] 1 MLJ 721 [2002] 2 MLJ 4 [2007] 3 MLJ 697 [2007] 5 MLJ 801 [2009] 8 MLJ 289 [2011] 6 MLJ 464 [2013] 1 MLJ 355 [2013] 6 MLJ 561 [2014] 6 MLJ 597 [2015] 6 MLJ 1 [2018] 1 MLJ 301 [2019] 6 MLJ 15 [2020] MLJU 1804

Judgment

Read the full judgment on the official Malaysia Courts portal.

Read on eJudgment

Source: eJudgment (ba-22ncvc-80-02-2023)