PEMBINAAN JAYA ZIRA SDN BHD v SUNGAI LUI CONSTRUCTION & DEVELOPMENT SDN BHD
wa-24carb-57-08-2024 High Court (Mahkamah Tinggi) 9 March 2025 • WA-24C(ARB)-57-08/2024 • 14 min read
9 cases cited
(0 SG, 9 foreign)
Catchwords
Judges (1)
Counsel (6)
Case Significance
PEMBINAAN JAYA ZIRA SDN BHD v SUNGAI LUI CONSTRUCTION & DEVELOPMENT SDN BHD is a High Court (Mahkamah Tinggi) decision dated March 9, 2025 (citation: wa-24carb-57-08-2024). The case was decided by Nadzarin bin Wok Nordin.
Key issues: Enclosure 1. Whereas in Originating Summons No. WA-24C(ARB)-57-08/2024 (OS 57), Pembinaan Jaya Zira Sdn Bhd (“PJZ”) had sought to set aside the Award on various grounds..
What was the outcome of PEMBINAAN JAYA ZIRA SDN BHD v SUNGAI LUI CONSTRUCTION & DEVELOPMENT SDN BHD?
PEMBINAAN JAYA ZIRA SDN BHD v SUNGAI LUI CONSTRUCTION & DEVELOPMENT SDN BHD is a High Court decision dated March 9, 2025. The case was heard by Nadzarin bin Wok Nordin. See the full judgment for details.
Statutes Cited
Arbitration Act 2005 (Cap 646)
Contracts Act 1950 (Cap 136)
Cases Cited (9)
MY (9)
[1996] 1 MLJ 178 [1996] 2 CLJ 249 [2006] 7 MLJ 510 [2010] MLJU 543 [2011] 1 CLJ 210 [2011] 6 AMR 573 [2011] 6 MLJ 441 [2012] 3 CLJ 423 [2023] 6 MLJ 345
Judgment
Read the full judgment on the official Malaysia Courts portal.
Read on eJudgmentSource: eJudgment (wa-24carb-57-08-2024)